Effectively communicates with the Contractor regarding all schedule/progress & project controls related matters and concerns in the weekly status meetings and all other schedule related meetings.
Reviews Contractor’s Baseline schedule submissions and verifies that all work scope is identified properly and logically sequenced correctly; provides written detailed schedule review comments. Coordinate with amazon stakeholders (Commissioning, Controls etc.) to ensure their scope, timeline and durations are accurate.
1) Validate the accuracy and assure the credibility of information contained in the schedule analysis performed by the Contractor.
2) Recommend ways to improve schedule performance through analysis, work-around, lessons learned, corrective actions and acceleration plans.
3) Analyze schedule impacts due to changes or claims, including time-impact analysis.
4) Performs Program Schedule QA/QC reviews on a weekly basis
5) Performs status updates for Program Schedules/Master Schedules on a weekly basis
6) Assist the Project Team in evaluating and monitoring the Contractors progress schedule as well as consulting and troubleshooting issues throughout the construction of the project.
7) Responsible for leading and training project managers and project controls specialists with reports for their assigned projects.
8) Review Schedule driven Change Orders and Time Impact/ Claims submitted from vendors
9) Walks the construction sites as needed and checks the contractor’s weekly/monthly schedule progress; provides reports to the project OAR and upper management.
10) Performs schedule Time Impact Analysis for any change orders that affect the construction schedule; conducts schedule negotiations with the OAR and the contractor for any delay time settlements